Is the supply chain under strain again, or is that just the feeling in this year's supplier meetings? Several public indicators answer the question with numbers, and at the end of November 2026 they point the same way: pressure is well above normal, though below the 2021 peak, and it has been for seven months. This guide reads the four indicators buyers can check for free, explains what each one measures, and turns them into practical decisions for the 2027 contracting round.
Key figures (latest available on 24 November 2026)
- 1.26: the New York Fed's Global Supply Chain Pressure Index for October 2026, i.e. 1.26 standard deviations above its long-run average. It has been above 0.9 every month since April.
- $4,176: Drewry's World Container Index per 40-foot container on 19 November 2026, down 3% on the week but 126% higher than a year earlier.
- 59.1: the ISM Supplier Deliveries Index for October 2026 in the US; any reading above 50 means deliveries are slowing.
- 75.2: the ISM Prices Index for October, down from 77.9 but still showing that most purchasing managers pay more than a month earlier.
1. The headline gauge: the New York Fed's GSCPI
The Global Supply Chain Pressure Index was created by economists at the Federal Reserve Bank of New York in 2022 to put a single number on something buyers had been describing anecdotally. It combines transport costs (container and bulk shipping rates, air freight from Asia to the US and Europe) with the supply-side components of purchasing managers' surveys in seven large economies: delivery times, backlogs and purchased stocks. The method is set out in the bank's staff report on the GSCPI. A reading of zero means pressure is at its average since 1997; each point is one standard deviation.
The shape is easy to read. The pandemic peak reached 4.43 in December 2021. By May 2023 the index had fallen to -1.56, meaning supply chains were looser than usual, and through 2024 and 2025 it hovered close to zero. Then it climbed: 0.55 in December 2025, 1.81 in April 2026, and between 0.95 and 1.36 every month from June to October. In May, PYMNTS reported that pressure had reached its highest level in nearly four years, noting that the New York Fed itself did not explain the increase but that, according to Reuters, it coincided with the war in the Middle East and the constraints it placed on the movement of goods.
Two cautions. First, the index is revised: the April figure was published as 1.82 and now stands at 1.81 in the bank's data file. Second, the bank warned in November 2025 that the index was being published with limited data while some inputs were suspended. Small month-to-month moves deserve less attention than the level.
2. Freight: the Drewry World Container Index
If the GSCPI is the thermometer, container rates are the part of it buyers feel first in landed costs. Drewry's weekly World Container Index fell 3% to $4,176 per 40-foot container on 19 November 2026, its fourth weekly decline, but remained 126% higher than a year earlier.
| Route (Drewry WCI, 19 Nov 2026) | US$ per 40ft | Week-on-week |
|---|---|---|
| Composite index | 4,176 | -3% |
| Shanghai – New York | 8,194 | -9% |
| Shanghai – Los Angeles | 7,026 | -5% |
| Shanghai – Genoa | 4,436 | +6% |
| Shanghai – Rotterdam | 3,496 | unchanged |
The routes diverge: transpacific rates are easing from high levels, while Asia–Mediterranean rates rose again. For a buyer, that means a single "freight is coming down" message from a supplier may be true on one lane and wrong on the one that matters to you. If a contract passes freight through at cost, ask which index or lane it is tied to.
3. Delivery times and prices: the ISM survey
The US Institute for Supply Management's monthly survey asks purchasing managers whether suppliers are delivering faster or slower, and whether they are paying more or less. In October 2026 the Supplier Deliveries Index stood at 59.1, against 59.0 in September; ISM noted that it indicated "slowing performance for the 11th month in a row". The Prices Index fell to 75.2 from 77.9, and inventories returned to growth at 51.4, as investingLive's summary of the report sets out. The headline Manufacturing PMI rose to 55.5.
Slower deliveries combined with a high prices index usually mean suppliers have pricing power. That matters for timing: a price review negotiated while lead times are still stretching is harder than one prepared now and opened when they stabilise.
4. Stockpiling: the GEP volatility index
The fourth signal comes from GEP's Global Supply Chain Volatility Index, based on a monthly survey of some 27,000 businesses. Its October release, published on 11 November, found that manufacturers accelerated precautionary stockpiling, sharply so in North America and Europe, even though overall pressure eased as shortages of materials and labour declined. Stockpiling is a self-reinforcing signal: when many buyers order ahead at once, they lengthen lead times for everyone else.
What the four indicators say together
Read side by side, they tell a consistent story. Pressure is elevated, not extreme: well above the calm of 2024–2025, a little over a quarter of the way back to the 2021 peak. Freight is the most volatile component and is falling on some lanes. Delivery times have not yet improved. And companies are building stock as insurance, which can prolong the squeeze. None of these numbers predicts the next shock; they describe the conditions you are negotiating in.
What buyers can do before the 2027 contracts
- Index the indexable. Where freight or energy is a large share of cost, link price adjustments to a named public index (a WCI lane, a published energy price) with a cap and floor, rather than accepting ad hoc surcharges. Our guide to total cost of ownership shows how to weigh those components.
- Re-check lead times in the master data. Planning systems often still carry 2025 lead times. With deliveries slowing for eleven months, update them for critical items, or reorder points will be wrong.
- Revisit single-supplier exposure. Elevated pressure is when one late supplier stops a line. The supplier risk framework and our note on mapping geopolitical exposure help decide where a second source is worth paying for.
- Agree what "force majeure" covers. Disruption linked to a conflict raises the question of who carries delay costs. Settle it in the contract wording now, not in a dispute later.
- Watch the indicators monthly. The GSCPI is published early each month, ISM on the first business day, and Drewry every Thursday. Three numbers on one page are enough for a monthly category review.
Which indicator does your team actually use in supplier negotiations? If it is none of the above, the GSCPI chart alone is a good place to start the conversation.
Methodology and sources
GSCPI values are taken from the New York Fed's data file (gscpi_data.xlsx) as downloaded on 24 November 2026, covering September 1997 to October 2026; the chart shows January 2019 onwards. Freight rates are Drewry's World Container Index assessment of 19 November 2026. ISM figures are from the October 2026 Manufacturing ISM Report On Business, released on 2 November 2026, as summarised by investingLive. The GEP index comes from its October 2026 release. Indices are published by their owners and may be revised; values here are as published on the dates given. Buyer's Ledger has no commercial relationship with any of these organisations. The chart and tables may be reused freely with a link to this page and credit to the original data sources. Last updated: 24 November 2026.
Suppliers & riskSupplier risk and resilience
Risk categories, multi-tier mapping, continuity planning and dual sourcing.
Suppliers & riskGeopolitics and supply chains
Chokepoints, sanctions, export controls and tariffs, and a method for mapping exposure.
Sourcing & negotiationTotal cost of ownership
Which costs to count before, during and after the purchase, and how to compare offers.